Construction & dust
Mass grading is underway. Residents documented visible dust and heavy construction activity during June and July.
What has changed, what the public record shows and what residents are still waiting to learn about the Hobart data center campus.
Two projects form the campus: Hobart Owner LLC proposed 6 buildings; TuHaus LLC proposed 20. Publicly available engineered plans showed 9 of the TuHaus buildings, while 11 were approved as a later phase without the same level of plan detail.
Mass grading is underway. Residents documented visible dust and heavy construction activity during June and July.
A July 24 filing describes 26 buildings and 782 diesel generators. It is an application under review—not a final operating permit.
The public record reviewed does not include the same engineered detail for the remaining 11 TuHaus buildings.
No commitment to an independent health study or public 24/7 air and noise monitoring was identified in the records reviewed.

In its mailer, Amazon states that contractors are using reinforced site entrances and street sweeping, water trucks, soil stabilization, wind protocols and daily inspections.
These photographs preserve what residents could see from public and neighborhood viewpoints on the dates shown.




The photos document visible conditions at specific moments. They do not independently determine particulate composition, concentration or whether a legal limit was exceeded. Use the Impact Log to add time, location, weather and supporting documentation.
Independent drone footage from BirdEyeView provides dated aerial views of grading and construction progress at the Hobart data center site. Select a video to compare how visible site conditions changed over time.
Early aerial documentation of the Hobart site.
Aerial view following local site-plan decisions.
Later-May view of grading and changing site conditions.
Mid-July aerial documentation of active construction areas.
Footage is credited to BirdEyeView and documents visible conditions on specific dates. It is independent of Hobart Residents FIRST and is not an official inspection or a determination of regulatory compliance.
These are not rhetorical questions. Each can be answered with a study, permit condition, monitoring plan, public dataset or binding agreement.
Where is the independent health-impact study addressing diesel exhaust, particulate matter, noise, stress and cumulative exposure?
Which protections are binding, who enforces them, what are the penalties and what remedy is available to affected residents?
Will neighborhood-scale PM2.5, PM10 and nitrogen-dioxide monitoring operate continuously, with real-time public data and independent oversight?
Will nighttime and low-frequency sound be continuously measured at property lines and nearby homes, with enforceable limits?
How many generators may test at once, on what schedule, with what advance notice and what limits during startup, testing and outages?
Where is the site-specific, multi-agency plan for fuel fires, battery incidents, electrical hazards, evacuation, mutual aid and public notification?
When will complete plans and impact analysis for the remaining 11 buildings be released before construction decisions are made?
Will independent inspectors verify construction controls, publish wind and inspection logs, and require prompt corrective action?
Report construction impacts, read the source documents and check upcoming meetings and resident actions.
Community Updates share clear, plain-language explanations of recent actions, decisions, and developments related to the proposed data center. This page provides context and timelines to help residents understand what’s happening and why it matters.
All referenced documents, permits, and meeting materials are posted in the Public Documents section of this site.
The City of Hobart issued a fill permit allowing grading and earthwork on property tied to the proposed Amazon data center development. While this may sound like a routine administrative step, fill permits can significantly alter land conditions and accelerate development before key questions are resolved.
In November, a fill permit covering approximately 178 acres was approved. A second, much larger fill permit covering approximately 605 acres is scheduled to be heard on February 5. Together, these permits would allow grading across a substantial portion of the project area.
At the same time, these permits are being considered without an approved site plan that shows the full layout, infrastructure, and impacts of the proposed development. In addition, funds associated with the project’s community benefit agreement have already begun to be paid despite the absence of an approved site plan.
Residents are concerned that significant land disturbance and financial commitments are moving forward before the complete project details are publicly reviewed.
A site plan is typically where the public and decision-makers can see how a project will function as a whole — including grading, drainage, access, utilities, and proximity to nearby uses. Approving permits and releasing community benefit funds without this context makes it difficult to evaluate cumulative impacts or ensure proper sequencing of approvals.
Once land is altered or funds are disbursed, those actions can be difficult to unwind, even if concerns arise later in the process.
Review of the proposed 605-acre fill permit scheduled for February 5
Continued monitoring of permit approvals in relation to site plan review
Ongoing public records requests to better understand approval sequencing
Date: December 2025 & January 2026
Community members filed two separate lawsuits related to actions taken by the City, Plan Commission, and Amazon Data Services in connection with the proposed Amazon data center development. Each lawsuit addresses a different part of the approval process and raises concerns about whether required procedures were followed.
Together, the lawsuits are part of an effort to ensure transparency, accountability, and compliance with established planning and zoning laws.
The lawsuits ask a court to review whether required processes were properly followed in two key areas:
Zoning Process Lawsuit:
Challenges actions related to rezoning, including whether the proper review sequence, hearings, and procedural requirements were met before zoning changes were approved.
Economic Revitalization Area (ERA) Lawsuit:
Challenges the establishment of the Economic Revitalization Area and related approvals tied to tax abatements and financial incentives, including whether those actions occurred before required development details were in place.
Both lawsuits focus on process and timing, not on speculation about future development.
The lawsuits:
Do not stop all City operations
Do not decide whether the project will ultimately be built
Do not replace public meetings or community input
Do not prevent residents from continuing to participate in the planning process
Legal review is one of several tools used to ensure decisions affecting the community follow the law.
Zoning changes and economic incentives can have long-term impacts on land use, infrastructure, and public finances. When residents believe these decisions were made without full procedural compliance or transparency, judicial review provides a structured way to seek clarity and accountability.
Regardless of outcome, clear process benefits both the community and decision-makers.
Court review of both filings
Continued monitoring of zoning, permits, and incentive-related actions
Ongoing public participation through meetings and public records review
Date: October 24, 2025
Community members submitted public records requests to better understand the approvals, communications, and documentation connected to the proposed data center development.
These requests seek clarity — not speculation — about what has been reviewed, approved, or discussed behind the scenes.
Public records laws exist to ensure transparency in government decision-making. When residents can review the same information as officials, discussions become more informed and productive.
Access to records helps answer key questions about:
Environmental review
Procedural compliance
Timing of approvals
Some records have been released, while others are pending or have been denied and are being evaluated for next steps. A few residents have been denied open records due to being named on the lawsuit even though some of these records pre-dated the filed complaint.
Reviewing received documents
Posting records publicly when possible
Continuing to request information necessary for transparency