Community Updates

Resident briefing • Updated July 29, 2026

Hobart Data Center Updates

What has changed, what the public record shows and what residents are still waiting to learn about the Hobart data center campus.

This update in 60 seconds

Current status

Two projects form the campus: Hobart Owner LLC proposed 6 buildings; TuHaus LLC proposed 20. Publicly available engineered plans showed 9 of the TuHaus buildings, while 11 were approved as a later phase without the same level of plan detail.

Active

Construction & dust

Mass grading is underway. Residents documented visible dust and heavy construction activity during June and July.

Pending review

State air application

A July 24 filing describes 26 buildings and 782 diesel generators. It is an application under review—not a final operating permit.

Record gap

11 buildings

The public record reviewed does not include the same engineered detail for the remaining 11 TuHaus buildings.

Unanswered

Resident protections

No commitment to an independent health study or public 24/7 air and noise monitoring was identified in the records reviewed.

Recent developments

What changed

July 24, 2026Amazon Data Services submitted an air-permit application covering both project sites as one source. The filing lists 782 emergency generators and applicant-calculated emissions under proposed operating limits.
July 7, 2026Amazon mailed nearby residents a construction update describing dust-control practices and promising regular project updates.
June 9, 2026A City records response to a request for project-specific emergency-preparedness material directed the requester to Lake County’s general emergency-management webpage; it did not identify a campus-specific plan.
June–July 2026Residents photographed visible dust, grading activity and conditions near surrounding roads and neighborhoods.
Company communication

Amazon’s dust commitments—and the public questions

Amazon construction update mailer sent to Hobart residents in July 2026

In its mailer, Amazon states that contractors are using reinforced site entrances and street sweeping, water trucks, soil stabilization, wind protocols and daily inspections.

What residents still need to know

  • Will wind, watering and inspection logs be made public?
  • Who independently verifies that the controls work?
  • What corrective action is required when visible dust leaves the site?
  • How quickly must complaints be investigated and answered?
  • When will the promised regular construction updates be published?
Resident documentation

Conditions observed near the site

These photographs preserve what residents could see from public and neighborhood viewpoints on the dates shown.

The photos document visible conditions at specific moments. They do not independently determine particulate composition, concentration or whether a legal limit was exceeded. Use the Impact Log to add time, location, weather and supporting documentation.

Independent visual record

Construction from above

Independent drone footage from BirdEyeView provides dated aerial views of grading and construction progress at the Hobart data center site. Select a video to compare how visible site conditions changed over time.

April 6, 2026

Early aerial documentation of the Hobart site.

May 11, 2026

Aerial view following local site-plan decisions.

May 29, 2026

Later-May view of grading and changing site conditions.

July 16, 2026

Mid-July aerial documentation of active construction areas.

Footage is credited to BirdEyeView and documents visible conditions on specific dates. It is independent of Hobart Residents FIRST and is not an official inspection or a determination of regulatory compliance.

Public-record tracker

What the reviewed records establish

Air-permit applicationFiled July 24Covers 26 buildings, 782 diesel generators and both project sites. Read the filing summary →
Campus-specific emergency planNot identifiedThe City’s June response linked to general Lake County emergency information rather than producing or identifying a campus-specific plan.
NDA-related public recordsNot produced via APRAA January City response declined production through the public-records request because of active litigation and directed the requester to the discovery process.
Plans for 11 TuHaus buildingsDetail gapThe reviewed public materials do not provide the same engineered plan detail shown for the first 9 buildings.
Accountability checklist

Questions awaiting enforceable answers

These are not rhetorical questions. Each can be answered with a study, permit condition, monitoring plan, public dataset or binding agreement.

Independent health review

Where is the independent health-impact study addressing diesel exhaust, particulate matter, noise, stress and cumulative exposure?

Enforceable protections

Which protections are binding, who enforces them, what are the penalties and what remedy is available to affected residents?

24/7 air monitoring

Will neighborhood-scale PM2.5, PM10 and nitrogen-dioxide monitoring operate continuously, with real-time public data and independent oversight?

24/7 noise monitoring

Will nighttime and low-frequency sound be continuously measured at property lines and nearby homes, with enforceable limits?

Generator operations

How many generators may test at once, on what schedule, with what advance notice and what limits during startup, testing and outages?

Emergency preparedness

Where is the site-specific, multi-agency plan for fuel fires, battery incidents, electrical hazards, evacuation, mutual aid and public notification?

Full buildout plans

When will complete plans and impact analysis for the remaining 11 buildings be released before construction decisions are made?

Dust oversight

Will independent inspectors verify construction controls, publish wind and inspection logs, and require prompt corrective action?

Help keep the community record current

Report construction impacts, read the source documents and check upcoming meetings and resident actions.

Hobart Residents FIRST — Data Center Watch • Fair, Informed, Responsible, Safe & Transparent Development

Community Updates share clear, plain-language explanations of recent actions, decisions, and developments related to the proposed data center. This page provides context and timelines to help residents understand what’s happening and why it matters.

All referenced documents, permits, and meeting materials are posted in the Public Documents section of this site.

Why We’re Challenging the Fill Permit

What Happened

The City of Hobart issued a fill permit allowing grading and earthwork on property tied to the proposed Amazon data center development. While this may sound like a routine administrative step, fill permits can significantly alter land conditions and accelerate development before key questions are resolved.

In November, a fill permit covering approximately 178 acres was approved. A second, much larger fill permit covering approximately 605 acres is scheduled to be heard on February 5. Together, these permits would allow grading across a substantial portion of the project area.

At the same time, these permits are being considered without an approved site plan that shows the full layout, infrastructure, and impacts of the proposed development. In addition, funds associated with the project’s community benefit agreement have already begun to be paid despite the absence of an approved site plan.

Residents are concerned that significant land disturbance and financial commitments are moving forward before the complete project details are publicly reviewed.

Why This Matters

A site plan is typically where the public and decision-makers can see how a project will function as a whole — including grading, drainage, access, utilities, and proximity to nearby uses. Approving permits and releasing community benefit funds without this context makes it difficult to evaluate cumulative impacts or ensure proper sequencing of approvals.

Once land is altered or funds are disbursed, those actions can be difficult to unwind, even if concerns arise later in the process.

What’s Next

  • Review of the proposed 605-acre fill permit scheduled for February 5

  • Continued monitoring of permit approvals in relation to site plan review

  • Ongoing public records requests to better understand approval sequencing

What the Lawsuits Do (and Don’t Do)

Date: December 2025 & January 2026

What Happened

Community members filed two separate lawsuits related to actions taken by the City, Plan Commission, and Amazon Data Services in connection with the proposed Amazon data center development. Each lawsuit addresses a different part of the approval process and raises concerns about whether required procedures were followed.

Together, the lawsuits are part of an effort to ensure transparency, accountability, and compliance with established planning and zoning laws.

What the Lawsuits Do

The lawsuits ask a court to review whether required processes were properly followed in two key areas:

  • Zoning Process Lawsuit:
    Challenges actions related to rezoning, including whether the proper review sequence, hearings, and procedural requirements were met before zoning changes were approved.

  • Economic Revitalization Area (ERA) Lawsuit:
    Challenges the establishment of the Economic Revitalization Area and related approvals tied to tax abatements and financial incentives, including whether those actions occurred before required development details were in place.

Both lawsuits focus on process and timing, not on speculation about future development.

What the Lawsuits Do Not Do

The lawsuits:

  • Do not stop all City operations

  • Do not decide whether the project will ultimately be built

  • Do not replace public meetings or community input

  • Do not prevent residents from continuing to participate in the planning process

Legal review is one of several tools used to ensure decisions affecting the community follow the law.

Why This Matters

Zoning changes and economic incentives can have long-term impacts on land use, infrastructure, and public finances. When residents believe these decisions were made without full procedural compliance or transparency, judicial review provides a structured way to seek clarity and accountability.

Regardless of outcome, clear process benefits both the community and decision-makers.

What’s Next

  • Court review of both filings

  • Continued monitoring of zoning, permits, and incentive-related actions

  • Ongoing public participation through meetings and public records review

Why We Filed Public Records Requests

Date: October 24, 2025

What Happened

Community members submitted public records requests to better understand the approvals, communications, and documentation connected to the proposed data center development.

These requests seek clarity — not speculation — about what has been reviewed, approved, or discussed behind the scenes.

Why This Matters

Public records laws exist to ensure transparency in government decision-making. When residents can review the same information as officials, discussions become more informed and productive.

Access to records helps answer key questions about:

  • Environmental review

  • Procedural compliance

  • Timing of approvals

What’s Been Received So Far

Some records have been released, while others are pending or have been denied and are being evaluated for next steps. A few residents have been denied open records due to being named on the lawsuit even though some of these records pre-dated the filed complaint. 

What’s Next

  • Reviewing received documents

  • Posting records publicly when possible

  • Continuing to request information necessary for transparency