Major public-record update

The Full Hobart Data Center Public Record

Utility plans and permit applications show that Amazon and NIPSCO are pursuing infrastructure for the Hobart campus. They do not prove that the project’s location, scale, approval process, health effects, emergency readiness, environmental impacts or net cost to residents have been independently evaluated and found acceptable.

Evidence updated July 27, 2026 · Hobart, Indiana

26data-center buildings listed in Amazon’s air application
782diesel emergency generators proposed
2,119 MWcombined listed backup-generating capacity
5.47Mgallons of listed diesel-tank capacity

Our position

This is not a debate over whether infrastructure exists.

The question is whether Hobart approved one of the largest industrial developments in our region with complete plans, meaningful public review, enforceable neighborhood protections and an honest accounting of the long-term costs.

A power pathway is not a health-impact study. A pending permit application is not an issued permit. A payment schedule is not a net fiscal analysis. And a city approval is not proof that the public was shown the complete project before the vote.

Claims in context

What the records prove—and what they do not

The pro-project claim

The utility agreements and planned generation provide a credible path forward.

The complete context

They document a proposed electric-service pathway. They do not independently evaluate whether a 725-plus-acre industrial campus beside established homes is appropriately sited or adequately regulated.

The pro-project claim

Amazon submitted an air-permit application under existing regulations.

The complete context

The 190-page filing is an application under IDEM review—not an issued permit. Requested synthetic-minor limits are not final, enforceable operating conditions. Residents deserve scrutiny of modeling, testing hours, simultaneous operation, monitoring, reporting and enforcement.

The pro-project claim

The campus and community agreements have already been approved.

The complete context

Approval does not resolve the pending legal and procedural objections. For the 20-building Hobart Tech Park component, engineered plans for nine buildings were available for public review while the commission’s action covered all 20. The remaining eleven buildings should not be treated as a minor detail.

The pro-project claim

The city will receive substantial payments and economic benefits.

The complete context

Gross payments are not the same as a net public benefit. A credible fiscal analysis must also account for abatements and exemptions, infrastructure, fire and emergency-response capacity, utility effects, environmental costs and impacts on schools, libraries, townships and residents.

The pro-project claim

Existing laws and permits will protect the public.

The complete context

The existence of regulations does not answer whether local standards are strong enough. Hobart still needs enforceable baseline and continuous air and noise monitoring, a project-specific emergency plan, transparent complaint reporting, property-value protections and independent oversight.

The approval gap

Local review and the state filing are not the same thing

Local approvals moved forwardRezoning, incentives, fill activity and site-plan actions advanced in stages.
May 7, 2026: Site-plan actionThe Plan Commission approved the six-building HDC component and the 20-building Tech Park component, although only nine Tech Park buildings had engineered plans available for public review.
July 2026: Amazon’s state air application became publicThe filing describes the full 26-building configuration, 782 generators and millions of gallons of fuel capacity.
The unresolved questionWhy was the full 26-building operating configuration used for state permitting when the public had not received complete engineered plans for eleven of the locally approved buildings?

Responsible oversight

What residents are still asking for

Independent health and environmental review

Not a developer presentation—an assessment of cumulative air, noise, water, traffic and community-health impacts.

Project-specific emergency planning

Documented preparation for generators, substations, fuel storage, batteries, hazardous materials and large-scale incidents.

Baseline and continuous monitoring

Publicly accessible air and noise data, clear complaint procedures and enforceable corrective-action requirements.

Independent net fiscal analysis

Benefits and payments weighed against exemptions, abatements, public-service demands and costs shifted onto residents.

Property and neighborhood protections

Property-value safeguards, strong setbacks, enforceable sound limits, screening, decommissioning security and transparent compliance.

Complete plans before future action

No treating eleven unreviewed building plans as a technicality after approval of an unprecedented industrial campus.

Transparency standard

Evaluate every source—including us

A polished website is not the same as an independent investigation. Readers should ask who authored a review, what expertise was used, who funded or commissioned it, whether contrary evidence was included and how corrections are handled.

Hobart Residents FIRST bases factual claims on public records, agency documents, meeting materials, court filings, official correspondence, credible reporting and clearly labeled resident observations. When a document is an application rather than an approval, or a projection rather than a guarantee, we will say so.

About the recent Northshore Gen review: its own homepage labels its conclusion as Northshore Gen’s assessment rather than an IDEM or IURC finding. We agree that residents should read the underlying records. We disagree that a documented infrastructure pathway answers the broader siting, process, health, fiscal and public-safety questions.

Read the records

Key documents behind this update

Amazon air-permit application

The pending application describes the proposed buildings, emergency engines, capacity, tanks and requested operating limits. Find the filing in our public-document library →

Local plans and legal filings

Review the city materials, site-plan records and court documents relevant to public notice, sequencing and plan completeness. Open the source library →

The recent pro-project review

Readers can compare our analysis with the review that prompted this update. Read Northshore Gen’s conclusion →

Put residents FIRST

What you can do now

  • Read the underlying permit and planning documents
  • Ask officials for complete plans and written answers
  • Support independent expert review
  • Document dust, noise, flooding, traffic and health concerns
  • Attend meetings and submit comments for the record
  • Share verified information—not rumors
Review Public DocumentsGet InvolvedOpen the Impact Log

The Resident-Led Data Center Impact Log documents construction and community impacts. It supplements—but does not replace—official complaints to the City, IDEM or another responsible agency.