Major public-record update
The Full Hobart Data Center Public Record
Utility plans and permit applications show that Amazon and NIPSCO are pursuing infrastructure for the Hobart campus. They do not prove that the project’s location, scale, approval process, health effects, emergency readiness, environmental impacts or net cost to residents have been independently evaluated and found acceptable.
Evidence updated July 27, 2026 · Hobart, Indiana
Our position
This is not a debate over whether infrastructure exists.
The question is whether Hobart approved one of the largest industrial developments in our region with complete plans, meaningful public review, enforceable neighborhood protections and an honest accounting of the long-term costs.
Claims in context
What the records prove—and what they do not
The utility agreements and planned generation provide a credible path forward.
They document a proposed electric-service pathway. They do not independently evaluate whether a 725-plus-acre industrial campus beside established homes is appropriately sited or adequately regulated.
Amazon submitted an air-permit application under existing regulations.
The 190-page filing is an application under IDEM review—not an issued permit. Requested synthetic-minor limits are not final, enforceable operating conditions. Residents deserve scrutiny of modeling, testing hours, simultaneous operation, monitoring, reporting and enforcement.
The campus and community agreements have already been approved.
Approval does not resolve the pending legal and procedural objections. For the 20-building Hobart Tech Park component, engineered plans for nine buildings were available for public review while the commission’s action covered all 20. The remaining eleven buildings should not be treated as a minor detail.
The city will receive substantial payments and economic benefits.
Gross payments are not the same as a net public benefit. A credible fiscal analysis must also account for abatements and exemptions, infrastructure, fire and emergency-response capacity, utility effects, environmental costs and impacts on schools, libraries, townships and residents.
Existing laws and permits will protect the public.
The existence of regulations does not answer whether local standards are strong enough. Hobart still needs enforceable baseline and continuous air and noise monitoring, a project-specific emergency plan, transparent complaint reporting, property-value protections and independent oversight.
The approval gap
Local review and the state filing are not the same thing
Responsible oversight
What residents are still asking for
Independent health and environmental review
Not a developer presentation—an assessment of cumulative air, noise, water, traffic and community-health impacts.
Project-specific emergency planning
Documented preparation for generators, substations, fuel storage, batteries, hazardous materials and large-scale incidents.
Baseline and continuous monitoring
Publicly accessible air and noise data, clear complaint procedures and enforceable corrective-action requirements.
Independent net fiscal analysis
Benefits and payments weighed against exemptions, abatements, public-service demands and costs shifted onto residents.
Property and neighborhood protections
Property-value safeguards, strong setbacks, enforceable sound limits, screening, decommissioning security and transparent compliance.
Complete plans before future action
No treating eleven unreviewed building plans as a technicality after approval of an unprecedented industrial campus.
Transparency standard
Evaluate every source—including us
A polished website is not the same as an independent investigation. Readers should ask who authored a review, what expertise was used, who funded or commissioned it, whether contrary evidence was included and how corrections are handled.
Hobart Residents FIRST bases factual claims on public records, agency documents, meeting materials, court filings, official correspondence, credible reporting and clearly labeled resident observations. When a document is an application rather than an approval, or a projection rather than a guarantee, we will say so.
About the recent Northshore Gen review: its own homepage labels its conclusion as Northshore Gen’s assessment rather than an IDEM or IURC finding. We agree that residents should read the underlying records. We disagree that a documented infrastructure pathway answers the broader siting, process, health, fiscal and public-safety questions.
Read the records
Key documents behind this update
Amazon air-permit application
The pending application describes the proposed buildings, emergency engines, capacity, tanks and requested operating limits. Find the filing in our public-document library →
IURC utility orders
Cause 46322 customer contract →
Cause 46362 generation arrangements →
Local plans and legal filings
Review the city materials, site-plan records and court documents relevant to public notice, sequencing and plan completeness. Open the source library →
The recent pro-project review
Readers can compare our analysis with the review that prompted this update. Read Northshore Gen’s conclusion →
Put residents FIRST
What you can do now
- Read the underlying permit and planning documents
- Ask officials for complete plans and written answers
- Support independent expert review
- Document dust, noise, flooding, traffic and health concerns
- Attend meetings and submit comments for the record
- Share verified information—not rumors
The Resident-Led Data Center Impact Log documents construction and community impacts. It supplements—but does not replace—official complaints to the City, IDEM or another responsible agency.