Explore the major zoning decisions, incentives, permits, lawsuits, construction activity and resident actions shaping the proposed 26-building data center campus.
How the project moved forward
Select a category, then open any event for context and source links. This highlights the major milestones; the downloadable PDF preserves the more detailed meeting-by-meeting record through January 25, 2026.
April-June 2022
155-acre industrial rezoning approved
Approval
Becknell Services requested rezoning near 61st Avenue and Colorado Street from R-3 residential to M-1 industrial. After being tabled, Ordinance 2022-11 passed 4-3.
Hobart Devco's 168-acre request advanced from the Plan Commission to the Council. Ordinance 2025-07 changed the property from R-3 to M-1 for the data center application.
First fill-permit action advances before a full site plan
Construction
The Plan Commission favorably recommended the fill-permit request for the 168-acre component. Residents questioned why grading approvals were advancing before full site-plan review.
December 8, 2025
Residents file a rezoning challenge
Legal
A lawsuit challenged the rezoning process. The original timeline identifies case number 45D11-2512-MI-000644.
Economic revitalization area and tax incentives approved
Incentives
The Council approved the economic revitalization area, real-property abatements and Amazon enterprise-information-technology exemption and community agreements.
A January 15 special meeting was cancelled because the fill-permit materials were not available for public inspection. The 605-acre request returned February 5.
March 2026
Court denies preliminary injunction; fill work continues
LegalConstruction
Residents sought to stop fill activity while litigation continued. The preliminary injunction was denied March 26.
Both site plans approved - but eleven buildings lacked plans
Approval
The Plan Commission approved the six-building Hobart Owner LLC component and the 20-building TuHaus LLC component. Engineered plans were shown for only nine of TuHaus's 20 buildings; the other eleven were described as a later phase.
Wetlands and water-quality review draws public concern
Environment
A Section 401 water-quality certification process identified proposed wetland and stream impacts. Residents requested additional time, a hearing and cumulative-impact review.
June-July 2026
Resident monitoring and public actions expand
Resident action
Residents documented dust, truck traffic and construction impacts, organized rallies and community conversations, and launched a resident-led impact log.
Amazon's state air application reveals the full 26-building configuration
Environment
The application lists 26 buildings, 782 backup diesel generators, 2,119 MW of combined backup-generating capacity and approximately 5.47 million gallons of listed diesel-tank capacity. The filing is an application under review, not an issued permit.
Last updated July 27, 2026. This page is a public-education summary. Open the source records for the complete language, procedural history and later amendments.