Public Documents & Records

This page contains public records, filings, notices, and official documents related to the proposed AI / Amazon Data Center project in Hobart. These documents are provided so residents can review what has been submitted, approved, or discussed by city officials and developers.

Transparency matters. We encourage everyone to read and stay informed.

Primary-source document library

Hobart Data Center Public Documents

Applications, plans, permits, ordinances, agreements and government records—organized so residents can find the source before relying on a claim.

Find records by subject

The library separates what an applicant requested from what an agency approved. Dates and document types matter: an application, staff report, meeting vote and final permit are not interchangeable.

Reading tip: Check the issuing agency, document date, project name and status. “Filed” means submitted for review; it does not necessarily mean approved or permitted.
Newest primary record

Air permit & diesel generators

Amazon Data Services air application — July 24, 2026

The application treats the two Hobart sites as one source and describes 26 buildings, 782 diesel generators and listed fuel-storage equipment. This is an applicant filing under agency review—not a final operating permit.

Open application PDF
WEB
Consolidated review

Full Public Record

Key figures, source citations, local approval gap and a claim-by-claim record review.

Read →
TIME
Project history

Interactive Data Center Timeline

Major zoning, incentive, permitting, litigation, construction and resident-action milestones.

Explore →
Local land-use record

Planning, zoning & site plans

520
Hobart Owner LLC • Complete six-building submission

SBN 520 — Six-Building Site Plan Set

Large plan set for the Hobart Data Center Campus component: six proposed data center buildings. Externally hosted on Google Drive.

Open plans →
750
TuHaus LLC • Drawings show 9 of 20 proposed buildings

SBN 750 — Nine-Building Site Plan Set

Plan set submitted for the Hobart Tech Park component. The drawings cover 9 buildings; the project approval referenced 20, leaving 11 without the same plan detail in this set.

Open plans →
CITY

Hobart Master Plan

City planning framework and adopted long-range land-use guidance.

Open →
CITY

Vision & Future Land Use

City land-use vision document used for planning context.

Open →
PDF
December 9, 2024

Zone Change Application

Applicant materials supporting the initial rezoning request.

PDF →
PDF
December 10, 2024

Data Center Layout Exhibit

Early layout exhibit showing the proposed development concept.

PDF →
PDF
December 10, 2024

Project Description

Applicant’s written description of the proposed project.

PDF →
PDF
December 9, 2024

Findings of Fact

Findings associated with the land-use decision.

PDF →
PDF
January 2, 2025

Rezoning Presentation

Presentation used during the rezoning process.

PDF →
PDF

Wylie Property Rezoning Request

Rezoning request associated with additional project property.

PDF →
Earthwork & water management

Construction, fill permits & stormwater

PDF

Hobart DEVCO Fill-Permit Application

Application materials for fill and grading activity on the Data Center Campus property.

PDF →
PLAN

Data Center Campus Full Plan Set

Plan set associated with the six-building Hobart Owner LLC project.

PDF →
SWPP

Construction SWPPP Technical Review

Technical review of the stormwater pollution prevention materials.

PDF →
SWPP

Data Center Campus SWPPP Report

Stormwater pollution prevention report for the campus project.

PDF →
PDF

Tech Park Fill-Permit Application

Application materials for mass grading on the TuHaus LLC Tech Park property.

PDF →
PLAN
December 9, 2025

Tech Park Mass-Grading Package

Plans and supporting documents for large-scale grading activity.

PDF →
SWPP
December 9, 2025

Tech Park Mass-Grading SWPPP

Stormwater pollution prevention materials for Tech Park grading.

PDF →
Regional power record

Power, utility & grid records

These official IURC and MISO records concern the regional utility, generation and transmission pathway associated with large-load service. They are not local land-use approvals, air permits, or proof that every proposed Hobart building has completed all required reviews.

IURCFinal order • September 24, 2025

Cause No. 46183 — GenCo Regulatory Framework

Commission order establishing the limited-jurisdiction framework for NIPSCO Generation LLC and generation facilities intended to serve megaload customers.

Official order →
IURCFinal order • June 17, 2026

Cause No. 46322 — Amazon Customer Contract & Power Purchase Agreement

Approves the NIPSCO–Amazon special contract, the NIPSCO–GenCo power purchase agreement and related regulatory treatment. The order describes service beginning in 2027 and ramping up to 2,400 MW by the end of 2032.

Official order →
IURCFinal order • June 17, 2026

Cause No. 46362 — GenCo Generation Resources

Commission order addressing the GenCo resource portfolio proposed to serve megaload demand, including gas-fired generation and battery storage.

Official order →
MISOApril 7, 2026 status update

Project 51141 — New Hobart Load Addition

MISO’s Expedited Project Review statistics identify a 1,500 MW “New Hobart Load Addition” submitted by NIPSCO and listed as approved. The record describes a transmission-planning project; it does not itself identify the customer or approve the data-center site.

Official MISO PDF →
MISOLiving project workbook

MTEP Projects Under Evaluation

MISO’s current project workbook contains the detailed listing for the New Hobart 345-kV load addition. Because this is a living workbook, readers should note the download date and confirm the latest status.

Official MISO workbook →
Important distinction: IURC approval of utility contracts and MISO transmission planning do not replace IDEM permitting, local site-plan review, USACE Section 404 review, IDEM Section 401 certification or other project-specific approvals that may apply.
Public finance

Tax incentives & agreements

These City archive records relate to incentive and agreement actions. Archive numbers are retained so readers can verify the original City source.

ERA
Resolution 2025-05 • City archive 1312

Economic Revitalization Area Declaration

Declares the mapped project area eligible for consideration of real- and personal-property tax deductions.

Open →
ERA
Resolution 2026-01 • City archive 1322

Economic Revitalization Area Confirmation

Confirms the Economic Revitalization Area following the declaratory resolution and public-hearing process.

Open →
TAX
Resolution 2026-02 • City archive 1323

Amazon / Hobart Tech Park Real-Property Tax Abatement

Approves the Amazon Data Services real-property abatement and includes the SB-1 statement and Hobart Tech Park Tax Abatement Agreement.

Open →
TAX
Resolution 2026-03 • City archive 1324

Hobart Owner LLC Real-Property Tax Abatement

Approves the Hobart Owner LLC abatement and includes the SB-1 statement and Hobart Devco Campus Tax Abatement Agreement.

Open →
CEA
Resolution 2026-04 • City archive 1325

Amazon IT Exemption & Community Enhancement Agreement

Approves the Enterprise Information Technology Exemption Agreement and Community Enhancement Agreement with Amazon Data Services.

Open →
Official City sources

Ordinances & archive records

Official City archive copies are linked directly. A future indexing pass will add the ordinance number, adoption date and plain-language subject beside each archive number.

Collection checklist

Documents still needed

These records are known, referenced or important to understanding the full project, but are not yet available in this organized library. “Needed” does not necessarily mean the document exists or has been approved.

Needed

May 7 site-plan approval records

Full applications, staff reports, findings, conditions and approved plan sets for both projects.

Needed

Plans for the remaining 11 buildings

Engineered drawings and supporting impact analysis comparable to the first nine Tech Park buildings.

Needed

Traffic study & revisions

Original study, reviewer comments, revised assumptions and any full-buildout analysis.

Needed

Drainage & geotechnical records

Final drainage calculations, ditch impacts, soil reports, reviewer comments and approved revisions.

Needed

Wetlands & federal records

IDEM 401 certification, USACE jurisdictional determination or permits, mitigation records and related maps.

Needed

Development and community agreements

Executed agreements, amendments, payment schedules, exhibits and performance obligations.

Needed

Tax-abatement record

ERA resolutions, SB-1/CF-1 filings, deduction schedules, findings and later compliance reviews.

Needed

Construction monitoring logs

Dust, wind, watering, inspection, complaint, violation and corrective-action records.

Needed

Emergency & fire coordination

Project-specific response plans, training records, mutual-aid planning and applicant communications.

Needed

Utility & energy agreements

Interconnection, transmission, GenCo, substation, water and sewer records available for public release.

Needed

Air and noise monitoring plans

Baseline studies, equipment locations, reporting rules, enforcement thresholds and public-data commitments.

Needed

Updated public communications

Amazon, developer, contractor and City construction notices or project updates not already archived.

Personal addresses, private email addresses and other unnecessary identifying information should be redacted before public posting. Legal pleadings and litigation-specific records belong in the separate Legal Record.

Have a public record that belongs here?

Send the original file with its source, date received and issuing agency. Please redact unnecessary personal information before sharing.

Free public access. Primary sources. No paywall.Hobart Residents FIRST — Data Center Watch • Fair, Informed, Responsible, Safe & Transparent Development

Complete Data Center Timeline - updated January 25th, 2026 (View Document) 

Planning & Zoning Documents

Official filings and zoning materials related to the proposed data center development.

Comprehensive Plan (View Document) 

Vision and Future Land Use - Page 6,11, & 12 (View Document) 

Rezoning Petitions/Applications - Rezoning documents showing how land-use changes were proposed, reviewed, and approved.

Ordinances - Ordinances passed by the City that govern zoning, development standards, and public policy decisions.

  • Ordinance 2024-33 Amend Code to M 1 Light Industrial Zones (View Document) ***No Plan Commission Public Hearing Held to change Municipal / Only passed by City Council 
  • Ordinance 2025-07 Changing an Est R-3 Zone to M-1-Zone (View Document) 
  • Ordinance 2025-22 Amends Municipal Code re Data Center Regulations (View Document) ***Repeat of Ord 2024-33 but added sound provision. Plan Commission Public Hearing Held 6/18/25 
  • Ordinance 2025-28 Changing R-3 Zone to M-1 Zone 61st and Colorado (View Document) 
  • Ordinance 2025-37 Vacate of ROW Hobart Devco (View Document) 

 

  • Staff reports

  • Comprehensive plan excerpts

  • Plan Commission materials

Permits & Applications

Documents related to fill permits, wetlands, water use, and environmental impact concerns.

Fill Permit Applications - Applications requesting approval to place fill on wetlands or undeveloped land.

  • Hobart Devco / Hobart Owner LLC (Approved Fill Permit on November 6th, 2025 without a Site Plan Review)
  • TUHAUS, LLC / Wylie Capital LLC (Fill Permit Hearing February 5th, 2026 still without a Site Plan Review; Also documents provided for inspection are incomplete)
  • Fill Permit Application (View Document) Fill Permit Mass Grading (View Document)
  • Construction/Stormwater Pollution Prevention Plan Technical Review (NOT PROVIDED) Stormwater Pollution Prevention Plan (SWPPP) (View Document)
  • Environmental permits

  • Building or site applications - NONE & Permits are already being approved without Site Plans

  • Preliminary approvals

Public Notices & Hearing Materials

Notices, agendas, minutes, and records from Plan Commission and city meetings related to this project.

Complete Data Center Timeline - updated January 25th, 2026 (View Document) 

  • Hearing notices

  • Agendas

  • Meeting minutes

  • Staff memos tied to meetings

Studies, Reports & Technical Materials

Environmental reviews, technical studies, and consultant analyses.

  • Environmental reviews - none 

  • Noise studies - none

  • Traffic or infrastructure reports 

  • Consultant analyses - none 

Correspondence & Public Records Requests

Letters, emails, and public records responses related to transparency and document access.

  • Emails with city officials

  • APRA requests

  • Responses to public records requests

  • Letters submitted by residents or groups

Tax Abatements & Economic Agreements

Documents related to proposed tax abatements, incentives, and economic impact claims.

Tax abatement documents

  • Resolution 2025-05 Declaring an Area with the City as an Economic Revitalization Area (View Document)
  • Resolution 2026-01 Confirming a Economic Revitalization Area 61st and Colorado SE corner (View Document)

  • Resolution 2026-02 Approving Real Property Tax Abatement Amazon Data Svcs (View Document)
  • Resolution 2026-03 Approving Real Property Tax Abatement Hobart Owner LLC (View Document)

Community benefit agreements 

  • Resolution 2026-04 Approving Enterprise IT Exmpt Agmt and Comm Enhance Agmt  Amazon Data Services (View Document)

Development agreements

Memorandums of understanding