SOPHIA: HIA Scoping for the Hobart Data Center Cluster
SOPHIA expressly states that this is a scoping report—not a completed HIA. It lays out a 16-to-20-week, nine-phase, independent and community-engaged assessment under SOPHIA Practice Standards. The proposed work would build a public baseline, examine the full project cluster and upstream energy buildout, compare alternatives, identify inequitable impacts, develop enforceable recommendations and establish ongoing public monitoring.